| Project ID |
Status |
% Complete |
Project Title
|
Work Order # |
Date Initiated |
Date Completed |
Documentation |
| P-1999-0022 |
COMPLETED |
100% |
Overhaul the Uplink
Satellite System
|
|
Tue 8/4/98 |
Fri 9/1/00 |
|
| P-1999-0029 |
COMPLETED |
100% |
Replace AVT system
(answers 7-1885)
|
|
Wed 1/20/99 |
Fri 9/1/00 |
|
| P-1999-0045 |
COMPLETED |
100% |
Engineering plan
for WMTU
|
FT103-1 |
Tue 8/24/99 |
Fri 12/1/00 |
P-1999-0045index.html |
| P-1999-0054 |
COMPLETED |
100% |
CS Department
10mb request
|
|
Tue 10/26/99 |
Sun 10/1/00 |
P-1999-0054index.html |
| P-1999-0056 |
COMPLETED |
100% |
NLANR Amp Project
|
|
NA |
Fri 9/1/00 |
|
| P-2000-0003 |
COMPLETED |
100% |
Rewire/Network
Upgrade for Chem. 204
|
FT104-1 |
Thu 1/27/00 |
Fri 9/15/00 |
P-2000-0003index.html |
| P-2000-0004 |
COMPLETED |
100% |
Library classroom
|
FT101-1 |
Fri 2/4/00 |
Tue 10/24/00 |
P-2000-0004index.html |
| P-2000-0012 |
COMPLETED |
100% |
ResNet TP Network
Upgrade
|
|
Tue 3/7/00 |
Fri 9/1/00 |
P-2000-0012index.html |
| P-2000-0019 |
COMPLETED |
100% |
Fisher/Sun Ray
Project
|
FT93-1, FT174-1, FT175-1 |
Fri 4/28/00 |
Fri 9/15/00 |
|
| P-2000-0023 |
COMPLETED |
100% |
Heights DSL Engineering
|
|
Fri 5/12/00 |
Mon 9/18/00 |
|
| P-2000-0028 |
COMPLETED |
100% |
Math Dept. Computer
Lab (Phase2)
|
FT122-1 |
Thu 7/20/00 |
Fri 9/15/00 |
|
| P-2000-0029 |
COMPLETED |
100% |
Library SunRay
project
|
FT126-1, NC664-1 |
Thu 7/27/00 |
Tue 12/5/00 |
|
| P-2000-0031 |
COMPLETED |
100% |
MEEM Server Room
Upgrade
|
FT127-1, NC550-1 |
Mon 8/14/00 |
Fri 10/20/00 |
|
| P-2000-0032 |
COMPLETED |
100% |
Credit Union Connections
|
FT128-1, AP1045-1 |
Wed 8/16/00 |
Fri 9/15/00 |
|
| P-2000-0034 |
COMPLETED |
100% |
Forestry Wideband
CATV connections
|
TV34-1 |
Mon 9/11/00 |
Mon 10/16/00 |
|
| P-2000-0036 |
COMPLETED |
100% |
IT Citrix Server
connections
|
NC623-1 |
NA |
Thu 11/2/00 |
|
| P-2000-0044 |
COMPLETED |
100% |
Created SNAP Service
|
FT209-1 |
NA |
Sun 8/27/00 |
|