Project Documentation for P-1999-0042

Date
Details
08/10/1999 Correspondence
11/16/1999 As of 11/16/99 staff meeting--informed that there is a problem with the ATM switch. Also the 2810 problems still needs to be addressed (if 2810 works--we need to order the new ATM switch & hubs.) Also informed that we still need to finish the plan.
03/07/2000 As of 3/7/00 staff meeting -- informed that Dan has completed the backbone drawing.
03/13/2000 As of 3/13/00 -- informed that a meeting was held with Bob B., Bob G., Jeff, and Steve. They will check into the accuracy of the drawing (feeds, fiber counts, distances, etc.) for the entire campus and will make updates as needed. Jeff will update port drawings and Bob B. will update DEC drawings as needed.
03/21/2000 As of 3/21/00 staff meeting -- informed that the biggest push is the single mode fiber. We need to install fiber between EERC & Fisher. Also Need to get to Ad bulding. Discussed specs of various fiber types. This is going to be a fiber per building model. Informed that there is currently a shortage of single-mode fiber. This will be done in two tiers. The first tier will include EERC, Fisher, ME, Dow & DHH. Second tier will include Walker, Library & Chem.