| 2/23/2000 | Project added to the list per correspondence |
| 2/29/2000 |
As of 2/29/00 staff meeting "Kurt & Steve have spoken to Rel about this. This project involves 8 jack locations. Rel wants the project completed ASAP. Discussed wiring issues such as availability of Cat6. Kurt needs to get Rel an estimate. It was determined to use Cat5E for this project. We need to get Bay Electric going on the project once we receive approval from Rel." |
| 3/07/2000 | As of 3/7/2000 staff meeting -- informed that the electricians finished yesterday. We are still waiting on Rel for the go ahead. |
| 3/21/2000 | As of 3/21/2000 staff meeting -- informed that cable has been received and that we are ready to start wiring tomorrow |
| 3/24/2000 | Correspondence regarding switch |
|