| 1/23/01 | Karen will be working with Nancy on entering all the interconnection information in Axis for all ES1200s and the ES2000s |
| 2/13/01 | Informed that the project is progressing. All interconnects have been entered for the ES1200s and the ES200s. Need a meeting to show everybody how the system works |
| 5/8/01 | Informed that Dan will check if ESRs are in AXIS |
| 7/10/01 | Informed that the info for the switch configuration needs to be reloaded. |
|